The layout, and which wastes, toilets, showers and walls move
Moving a waste or a wall drives cost and every later stage.
Ask: Is anything that drains moving? Check the fall to the sewer before you commit.
Every decision with a deadline for the bathroom and ensuite, in build order. Whole-house items are included.
Before anything is pulled out or ordered. Layout, what moves, and what has a long lead time. The cheapest stage to change your mind.
Moving a waste or a wall drives cost and every later stage.
Ask: Is anything that drains moving? Check the fall to the sewer before you commit.
It sets how the floor is built and how deep the screed is.
Ask: Can the floor be set down, or do you need a hob or linear drain to get the entry you want?
Each one needs framing, so it has to be known before the carpenter starts.
Ask: Which items sit in the wall rather than on it?
Some take weeks or months to arrive, longer than the gap to the stage that needs them.
Ask: What has a lead time longer than the time until it is needed?
Livable housing rules, for example, apply differently by state and not at all in some. source
Ask: Have you asked your certifier or builder which rules apply to this job?
Before the carpenter frames or re-frames walls. Anything recessed or wall-hung. The carpenter frames to the actual product.
The carpenter frames the opening to the product. A different cabinet later means re-framing.
Ask: Is the cabinet in hand, or its spec sheet final? The framer needs the real size, not an estimate.
It is framed now and tiled later, so its size should suit whole tiles. source
Ask: Is the niche sized to whole tiles, clear of the mixer, and between studs? A common base height is 900 to 1100 mm. Choose it here
The frame sets the pan height, the button height and the wall depth.
Ask: Which frame, and does it suit your pan and your wall depth?
Wall-hung items need a frame or heavy blocking behind them.
Ask: What is hanging off the wall, and what does its install sheet ask for behind it?
A floor-mounted filler can't be added once the floor is poured or screeded. source
Ask: If the filler comes up through the floor, is its position fixed now?
Openings are framed now. Where livable housing rules apply, doors need an 820 mm clear opening. source
Ask: Which doors are sliders, and do the openings meet any rule that applies to you?
A sill that clips the splashback or the tap is a framing fix, not a tiling one.
Ask: Does every sill clear the bench, splashback and taps under it?
Before the plumber and electrician run pipes and cables. Everything that sits in the wall or ceiling. Most variations start here.
In-wall mixer bodies are brand-specific. The trim must match the body already in the wall.
Ask: Is the trim you want the same brand as the body going in now?
The outlets are fixed in the wall. Roses usually sit 2000 to 2200 mm and mixers about 1000 to 1200 mm. source
Ask: Rail or arm? Have you set the heights from the finished floor?
It sets the falls and should sit on the tile grid.
Ask: Will the waste land on a tile joint, and which way does the floor fall to it? Choose it here
It sets the waste and supply heights, and the spout is set off the basin rim. Tops usually sit 850 to 900 mm. source
Ask: What height is the finished top, and how high is the basin rim above it?
Pans are set out at 140 or 165 mm from the wall. The waste is placed to suit the pan. source
Ask: Which pan, and which set-out does its install sheet give?
It sets pipe runs and power or gas. Water at basins, baths and showers is limited to 50 degrees C. source
Ask: Where does the hot water unit go, and how far is the longest run?
Cables go in before the walls close. Power points are usually about 300 mm high and switches about 1000 to 1200 mm, by convention, not code. source
Ask: Have you walked each room with the furniture: bedsides, desk, TV, benches, robe, appliances?
AS/NZS 3000 sets zones around showers and baths that limit what can go where. source
Ask: Has your electrician checked every point near water against the wet-area zones?
Each needs a point at the height its install sheet gives, and the fan needs a duct.
Ask: Do you have the install sheet for each powered item?
All run in the walls and ceiling. Smoke alarm rules differ by state.
Ask: Have you checked your state's smoke alarm rules, and where the AC drain runs?
Before the floor is screeded and the room is set out. Tile size, bedding depth and falls. Every height in the room is measured from the finished floor this sets.
It sets the joint lines, the cuts and where the waste sits. You can pick the exact colour later.
Ask: Do you know the tile size, so the floor and the waste can be set out? Choose it here
Allow about 40 to 50 mm. It moves the finished floor, and every height in the room is measured from the finished floor.
Ask: Have you allowed 40 to 50 mm for bedding? Your heights are from the finished floor, not the slab.
About 15 to 25 mm is added to the wall face, which moves outlets, niches and set-outs. source
Ask: Have pipe and outlet depths allowed for the finished wall face?
Wet-area falls are set by the NCC and AS 3740. Get them wrong and water sits or escapes. source
Ask: Have your tiler and waterproofer agreed the falls and the shower entry?
Every fixture height is from the finished floor. Mark it once, then set out from it.
Ask: Is there a datum line on the studs before anything is set out?
Tile next to timber or carpet needs matching heights and a trim.
Ask: Do the finished floor levels line up at every doorway?
Before the membrane goes on. Membrane heights and details. Can't be redone once tiled.
Shower walls are waterproofed to at least 1800 mm (or 50 mm above the rose if higher), with 40 mm each side of wall junctions. source
Ask: Does your waterproofer's scope meet the NCC heights?
These are the leak points, and they are buried once tiled.
Ask: Is every waste flanged, and is the niche sill falling back into the shower?
Before the walls and ceilings are sheeted. Blocking behind every fixing, and the plasterboard finish level.
Once the sheet is on, adding it means cutting the wall. Where livable housing rules apply, grab-rail walls need 12 mm ply or 25 mm noggings. source
Ask: Has every fixing point got blocking, photographed before sheeting?
Level 4 is standard. Gloss paint, dark colours and raking light need Level 5, which is set when the board is stopped, not painted. source
Ask: Are any walls going gloss, dark, or in raking light?
Wet areas take a water-resistant board under the membrane and tile.
Ask: Is wet-area board specified for every wet wall?
Before the tiler sets out. Tile heights, grout, trims and slip ratings. The tiler sets out from these on day one.
The tiler sets out from these. Keep one skirting height on every wall; a height that changes is the first thing people notice.
Ask: For each wall: floor to where?
Pale floor grout tends to go grey; epoxy needs no sealing and suits showers but costs more.
Ask: Have you seen the grout beside the real tile, in the room's own light? Choose it here
Trims show on every external corner and should match the tapware finish.
Ask: Which edges get a trim, and in what finish?
Two trades meeting on one line shows every millimetre of tolerance. Keep the top of a mirror cabinet off the tile line, about 100 mm below it.
Ask: Do any edges from two different trades land on the same line?
P3 is the usual minimum for bathroom floors; P4 or P5 for outdoors, ramps and pool surrounds.
Ask: Does each floor tile carry a published P rating that suits where it goes? Choose it here
Before cabinets and benchtops are ordered. Measure what was built, not what was drawn, then lock boards, benchtops and appliances.
The edge profile can move the price more than the colour does.
Ask: Which edge, which thickness, and where are the overhangs? Choose it here
Boards are ordered with the cabinets.
Ask: Have you seen the board sample next to the benchtop and the floor? Choose it here
Before the painter quotes and starts. Colours, sheen, prep and coats, per surface.
The painter quotes per surface.
Ask: Have you put real samples on your own walls, in the room's light? Choose it here
Ceilings are usually flat, walls low sheen, and wet areas, trims and doors semi-gloss or gloss.
Ask: Is the sheen written next to every colour in the painter's scope?
Quotes differ most on prep and coats. Master Painters recommend three coats on new work. source
Ask: Does every quote state the prep and the coats, so you can compare them?
At the end. The choices you can safely leave late: positions are already fixed.
Positions were fixed at rough-in, so the fitting itself can be chosen late.
Ask: Do the fittings suit the points already in the ceiling?
The blocking is already in, so these can wait.
Ask: Do the finishes match the tapware?
Screens are measured after tiling.
Ask: Has the screen been measured off the finished tiles?
Nothing else depends on them.
Ask: Did the power points land where the furniture went?
Prompts, not rules. Most choices can wait; these can't, because a later trade builds to them. Code items cite their source; states adopt parts of the NCC differently, so check yours. Your builder, trades, certifier and each product's install sheet decide. Download the list (JSON, CC BY 4.0).