The layout, and which wastes, toilets, showers and walls move
Moving a waste or a wall drives cost and every later stage.
Ask: Is anything that drains moving? Check the fall to the sewer before you commit.
Before anything is pulled out or ordered. Layout, what moves, and what has a long lead time. The cheapest stage to change your mind.
Moving a waste or a wall drives cost and every later stage.
Ask: Is anything that drains moving? Check the fall to the sewer before you commit.
The joinery is built around their cut-outs and clearances.
Ask: Do you have the spec sheet, with cut-out sizes, for every appliance?
It sets how the floor is built and how deep the screed is.
Ask: Can the floor be set down, or do you need a hob or linear drain to get the entry you want?
Each one needs framing, so it has to be known before the carpenter starts.
Ask: Which items sit in the wall rather than on it?
Some take weeks or months to arrive, longer than the gap to the stage that needs them.
Ask: What has a lead time longer than the time until it is needed?
Livable housing rules, for example, apply differently by state and not at all in some. source
Ask: Have you asked your certifier or builder which rules apply to this job?
Prompts, not rules. Most choices can wait; these can't, because a later trade builds to them. Code items cite their source; states adopt parts of the NCC differently, so check yours. Your builder, trades, certifier and each product's install sheet decide. Download the list (JSON, CC BY 4.0).