The layout, and which wastes, toilets, showers and walls move
Moving a waste or a wall drives cost and every later stage.
Ask: Is anything that drains moving? Check the fall to the sewer before you commit.
Every decision with a deadline for the kitchen, in build order. Whole-house items are included.
Before anything is pulled out or ordered. Layout, what moves, and what has a long lead time. The cheapest stage to change your mind.
Moving a waste or a wall drives cost and every later stage.
Ask: Is anything that drains moving? Check the fall to the sewer before you commit.
The joinery is built around their cut-outs and clearances.
Ask: Do you have the spec sheet, with cut-out sizes, for every appliance?
Each one needs framing, so it has to be known before the carpenter starts.
Ask: Which items sit in the wall rather than on it?
Some take weeks or months to arrive, longer than the gap to the stage that needs them.
Ask: What has a lead time longer than the time until it is needed?
Livable housing rules, for example, apply differently by state and not at all in some. source
Ask: Have you asked your certifier or builder which rules apply to this job?
Before the carpenter frames or re-frames walls. Anything recessed or wall-hung. The carpenter frames to the actual product.
Wall-hung items need a frame or heavy blocking behind them.
Ask: What is hanging off the wall, and what does its install sheet ask for behind it?
Openings are framed now. Where livable housing rules apply, doors need an 820 mm clear opening. source
Ask: Which doors are sliders, and do the openings meet any rule that applies to you?
A sill that clips the splashback or the tap is a framing fix, not a tiling one.
Ask: Does every sill clear the bench, splashback and taps under it?
The duct runs through the ceiling or wall before linings. Over gas, the hood must be at least 650 mm above the cooktop. source
Ask: Where does the duct go, and is the hood at least 650 mm above a gas cooktop?
Before the plumber and electrician run pipes and cables. Everything that sits in the wall or ceiling. Most variations start here.
In-wall mixer bodies are brand-specific. The trim must match the body already in the wall.
Ask: Is the trim you want the same brand as the body going in now?
It sets pipe runs and power or gas. Water at basins, baths and showers is limited to 50 degrees C. source
Ask: Where does the hot water unit go, and how far is the longest run?
Cables go in before the walls close. Power points are usually about 300 mm high and switches about 1000 to 1200 mm, by convention, not code. source
Ask: Have you walked each room with the furniture: bedsides, desk, TV, benches, robe, appliances?
Each sits at a position the appliance's spec sheet sets.
Ask: Is every appliance's point placed to its spec sheet, not a guess?
All run in the walls and ceiling. Smoke alarm rules differ by state.
Ask: Have you checked your state's smoke alarm rules, and where the AC drain runs?
Before the floor is screeded and the room is set out. Tile size, bedding depth and falls. Every height in the room is measured from the finished floor this sets.
It sets the joint lines, the cuts and where the waste sits. You can pick the exact colour later.
Ask: Do you know the tile size, so the floor and the waste can be set out? Choose it here
Tile next to timber or carpet needs matching heights and a trim.
Ask: Do the finished floor levels line up at every doorway?
Before the walls and ceilings are sheeted. Blocking behind every fixing, and the plasterboard finish level.
Once the sheet is on, adding it means cutting the wall. Where livable housing rules apply, grab-rail walls need 12 mm ply or 25 mm noggings. source
Ask: Has every fixing point got blocking, photographed before sheeting?
Level 4 is standard. Gloss paint, dark colours and raking light need Level 5, which is set when the board is stopped, not painted. source
Ask: Are any walls going gloss, dark, or in raking light?
Before the tiler sets out. Tile heights, grout, trims and slip ratings. The tiler sets out from these on day one.
The tiler sets out from these. Keep one skirting height on every wall; a height that changes is the first thing people notice.
Ask: For each wall: floor to where?
Pale floor grout tends to go grey; epoxy needs no sealing and suits showers but costs more.
Ask: Have you seen the grout beside the real tile, in the room's own light? Choose it here
Trims show on every external corner and should match the tapware finish.
Ask: Which edges get a trim, and in what finish?
It meets the benchtop, the cupboards and the rangehood, so the junctions need deciding.
Ask: Where does the splashback stop at each end and at the top? Choose it here
Before cabinets and benchtops are ordered. Measure what was built, not what was drawn, then lock boards, benchtops and appliances.
Drawings can be well out. Laser-measure the finished walls, then order.
Ask: Have the cabinet sizes been checked against a site measure after linings?
The edge profile can move the price more than the colour does.
Ask: Which edge, which thickness, and where are the overhangs? Choose it here
Boards are ordered with the cabinets.
Ask: Have you seen the board sample next to the benchtop and the floor? Choose it here
Stone is templated around the real sink, tap and cooktop. Without them, expect a return visit.
Ask: Are the sink, tap and cooktop on site when the templater comes?
Benches usually sit 900 to 950 mm, and the top of a wall oven no higher than about 1700 mm, by convention. source
Ask: Have you checked the bench height against the tallest and shortest cook?
Before the painter quotes and starts. Colours, sheen, prep and coats, per surface.
The painter quotes per surface.
Ask: Have you put real samples on your own walls, in the room's light? Choose it here
Ceilings are usually flat, walls low sheen, and wet areas, trims and doors semi-gloss or gloss.
Ask: Is the sheen written next to every colour in the painter's scope?
Quotes differ most on prep and coats. Master Painters recommend three coats on new work. source
Ask: Does every quote state the prep and the coats, so you can compare them?
At the end. The choices you can safely leave late: positions are already fixed.
Positions were fixed at rough-in, so the fitting itself can be chosen late.
Ask: Do the fittings suit the points already in the ceiling?
The blocking is already in, so these can wait.
Ask: Do the finishes match the tapware?
Nothing else depends on them.
Ask: Did the power points land where the furniture went?
Prompts, not rules. Most choices can wait; these can't, because a later trade builds to them. Code items cite their source; states adopt parts of the NCC differently, so check yours. Your builder, trades, certifier and each product's install sheet decide. Download the list (JSON, CC BY 4.0).